4STEP #4227

진행중

ProjectTask

dain Integrated Management System이(가) 9달 전에 추가함. 17일 전에 수정됨.

상태:
Proceeding
우선순위:
normal
담당자:
-
시작일:
01/01/2025
완료일:
12/31/2025 (기한 23일)
진척도:

65%

추정시간:
(합계: 2651:00 시간)

설명

프로젝트 시작


하위 일감 99 (40 건 진행 중59 건 완료)

4STEP #4228: 1.1 ReportPlanned02/28/202503/01/2025

Actions
4STEP #4235: 1.1.1 Progress ReportPlanned02/28/202503/01/2025

Actions
4STEP #4229: 1.2 PlanPlanned02/28/202503/01/2025

Actions
4STEP #4236: 1.2.1 WBSPlanned02/28/202503/01/2025

Actions
4STEP #4237: 1.2.2 TFT SettingPlanned02/28/202503/01/2025

Actions
4STEP #4238: 1.2.3 Product Requirement DocumentPlanned02/28/202503/01/2025

Actions
4STEP #4239: 1.2.4 Menu TreePlanned02/28/202503/01/2025

Actions
4STEP #4240: 1.2.5 IAPlanned02/28/202503/01/2025

Actions
4STEP #4241: 1.2.6 SBPlanned02/28/202503/01/2025

Actions
4STEP #4242: 1.2.6.1 AdminPlanned02/28/202503/01/2025

Actions
4STEP #4243: 1.2.6.2 ClientPlanned02/28/202503/01/2025

Actions
4STEP #4244: 1.2.7 Test ScenarioPlanned02/28/202503/01/2025

Actions
4STEP #4230: 1.3 DesignPlanned02/03/202510/31/2025

Actions
4STEP #3661: DT_추가 위성 4기, 안테나 10기 3D 모델링PlannedMoon Sunwoo02/03/202509/30/2025

Actions
4STEP #3633: DT 인공위성 1기(K5) 외형 3D 모델링CompleteKim Dongnam02/03/202502/21/2025

Actions
4STEP #3634: DT 인공위성 1기(K5) 내장 하드웨어 3D 모델링CompleteKim Dongnam02/24/202502/28/2025

Actions
4STEP #3635: DT 인공위성 2기(K3) 외형 3D 모델링CompleteLim Eunseo02/05/202503/28/2025

Actions
4STEP #3636: DT 인공위성 2기(K3) 내장 하드웨어 3D 모델링CompleteLim Eunseo02/26/202503/28/2025

Actions
4STEP #3637: DT 인공위성 3기(K3A) 외형 3D 모델링CompleteLim Eunseo03/06/202504/25/2025

Actions
4STEP #3638: DT 인공위성 3기(K3A) 내장 하드웨어 3D 모델링CompleteLim Eunseo03/27/202504/02/2025

Actions
4STEP #3640: 안테나 1기 외형 3D 모델링CompleteKang Sieun04/07/202504/11/2025

Actions
4STEP #3641: 안테나 1기 내장 하드웨어 or 장비렉, 서버 3D 모델링CompleteKang Sieun04/14/202508/29/2025

Actions
4STEP #3642: 안테나 2기 외형 3D 모델링CompleteLim Eunseo04/21/202504/25/2025

Actions
4STEP #3644: 안테나 2기 내장 하드웨어 or 장비렉, 서버 3D 모델링CompleteLim Eunseo04/28/202508/29/2025

Actions
4STEP #3645: 안테나 3기 외형 3D 모델링CompleteKim Dongnam05/05/202505/09/2025

Actions
4STEP #3646: 안테나 3기 내장 하드웨어 or 장비렉, 서버 3D 모델링CompleteKim Dongnam05/12/202508/29/2025

Actions
4STEP #3647: 안테나 4기 외형 3D 모델링CompleteKang Sieun07/21/202508/29/2025

Actions
4STEP #3648: 안테나 4기 내장 하드웨어 or 장비렉, 서버 3D 모델링CompleteKang Sieun08/04/202508/29/2025

Actions
4STEP #3649: 안테나 5기 외형 3D 모델링CompleteLim Eunseo07/21/202508/29/2025

Actions
4STEP #3650: 안테나 5기 내장 하드웨어 or 장비렉, 서버 3D 모델링CompleteKang Sieun08/04/202509/30/2025

Actions
4STEP #3651: 안테나 6기 외형 3D 모델링CompleteKang Sieun09/01/202509/14/2025

Actions
4STEP #3652: 안테나 6기 내장 하드웨어 or 장비렉, 서버 3D 모델링CompleteKang Sieun09/01/202509/30/2025

Actions
4STEP #3653: 안테나 7기 외형 3D 모델링CompleteKang Sieun09/01/202509/14/2025

Actions
4STEP #3654: 안테나 7기 내장 하드웨어 or 장비렉, 서버 3D 모델링CompleteKang Sieun09/01/202509/30/2025

Actions
4STEP #6258: 안테나 8기 외형 3D 모델링CompleteKim Dongnam09/01/202509/14/2025

Actions
4STEP #6259: 안테나 8기 내장 하드웨어 or 장비렉, 서버 3D 모델링CompleteKim Dongnam09/01/202509/30/2025

Actions
4STEP #6260: 안테나 9기 외형 3D 모델링CompleteKim Dongnam09/01/202509/14/2025

Actions
4STEP #6261: 안테나 9기 내장 하드웨어 or 장비렉, 서버 3D 모델링ProceedingKim Dongnam08/18/202509/30/2025

Actions
4STEP #7631: DT 인공위성 4기(NeonSAT) 외형 3D 모델링CompleteKim Dongnam08/18/202509/30/2025

Actions
4STEP #4610: DT 1차년도 인공위성, 안테나 3D 모델링 최적화 작업Complete03/10/202503/31/2025

Actions
4STEP #4608: DT 1차년도 인공위성 CAS500-1 3D 모델링 최적화 작업CompleteKim Dongnam03/10/202503/31/2025

Actions
4STEP #4609: DT 1차년도 안테나 J13 3D 모델링 최적화 작업CompleteKang Sieun03/10/202503/14/2025

Actions
4STEP #5498: 지구 2D맵 수정CompleteMoon Sunwoo05/01/202505/21/2025

Actions
4STEP #5499: 제주 인공위성 센터 지형 구현CompleteKim Dongnam05/01/202505/21/2025

Actions
4STEP #6262: 지구 2D 미니맵 낮/밤 표시CompleteMoon Sunwoo07/14/202508/08/2025

Actions
4STEP #6263: 2D 지구맵 지도 춘분/하지/추분/동지 맵 적용CompleteMoon Sunwoo07/14/202508/08/2025

Actions
4STEP #6264: NET 전용 2D 지도 제작PlannedMoon Sunwoo09/01/202510/31/2025

Actions
4STEP #6965: 지구 2D맵 절기별 텍스쳐 작업CompleteMoon Sunwoo07/14/202507/25/2025

Actions
4STEP #4231: 1.4 PublishingPlanned02/28/202502/28/2025

Actions
4STEP #4232: 1.5 DevelopmentProceeding01/01/202512/31/2025

Actions
4STEP #7036: DTProceeding06/23/202511/28/2025

Actions
4STEP #7038: 그래프 Morphing 효과 및 InteractionMission Timeline Grouping( X-CNT)Completehwang jinouk06/23/202507/04/2025

Actions
4STEP #7039: 위성 자세 변환Completehwang jinouk06/23/202507/11/2025

Actions
4STEP #7040: 다대다 통신Completehwang jinouk06/23/202507/11/2025

Actions
4STEP #7041: 모듈 뷰 새창 타임라인 연동Completehwang jinouk07/14/202507/18/2025

Actions
4STEP #7042: User Management & 권한 & 로그인Completehwang jinouk06/30/202507/25/2025

Actions
4STEP #7043: 안테나 Singal Level(Frequency) Pointing Accuracy(SAT)Pendinghwang jinouk09/22/202510/17/2025

Actions
4STEP #7044: 북마크,레코드,불러오기Completehwang jinouk08/04/202508/08/2025

Actions
4STEP #7045: 타임라인 배속Completehwang jinouk08/11/202508/22/2025

Actions
4STEP #7046: MPS 니모닉 TLM VerifyProceedinghwang jinouk11/17/202511/28/2025

Actions
4STEP #7047: 위성/장비 니모닉 3D 맵핑Completehwang jinouk07/07/202507/11/2025

Actions
4STEP #7048: 위성/안테나 추가Completehwang jinouk09/01/202510/31/2025

Actions
4STEP #7049: 카드뷰(일반,궤도)Completehwang jinouk07/07/202507/11/2025

Actions
4STEP #7050: 예측,실제 궤도선Completehwang jinouk08/18/202510/31/2025

Actions
4STEP #7037: FDSProceeding01/01/202512/31/2025

Actions
4STEP #7054: Scheduler 프론트 구현Completekim miseon07/07/202507/11/2025

Actions
4STEP #7055: Scheduler 백엔드 구현Plannedhwang jinouk10/15/202510/31/2025

Actions
4STEP #7056: Scheduler API 구현 및 연동Proceedinghwang jinouk10/13/202510/31/2025

Actions
4STEP #7057: Script 프론트 구현Completekim miseon07/14/202507/25/2025

Actions
4STEP #7058: Script 백엔드 구현Proceedinghwang jinouk08/11/202510/31/2025

Actions
4STEP #7059: Script API 구현 및 연동Proceedinghwang jinouk09/10/202510/31/2025

Actions
4STEP #7060: Report 프론트 구현Completekim miseon07/28/202508/08/2025

Actions
4STEP #7061: Report 백엔드 구현Plannedhwang jinouk11/03/202511/30/2025

Actions
4STEP #7062: Report API 구현 및 연동Plannedhwang jinouk11/01/202511/28/2025

Actions
4STEP #7063: FA 프론트 구현 Completekim miseon08/11/202508/13/2025

Actions
4STEP #7067: OD 프론트 구현 Completekim miseon05/26/202505/30/2025

Actions
4STEP #7071: OP 프론트 구현 Completekim miseon06/02/202506/05/2025

Actions
4STEP #7072: OP 데이터 및 알고리즘 분석Proceedinghwang jinouk10/01/202510/31/2025

Actions
4STEP #7073: OP 유니티 구현Plannedhwang jinouk10/20/202511/28/2025

Actions
4STEP #7074: OP API 구현 및 연동Plannedhwang jinouk10/20/202511/21/2025

Actions
4STEP #7075: OM 프론트 구현 Completekim miseon08/14/202508/19/2025

Actions
4STEP #7079: AD 프론트 구현 Completekim miseon08/20/202508/22/2025

Actions
4STEP #7090: ICD 문서 작성(interface 문서 및 Diagram)Proceedinghwang jinouk01/01/202512/31/2025

Actions
4STEP #7421: Add Satellite/Satellite Setting 프론트 구현Completekim miseon08/11/202508/18/2025

Actions
4STEP #7422: Add Satellite - 3D 프론트 구현Completekim miseon08/11/202508/22/2025

Actions
4STEP #7423: Satellite Setting - FA 프론트 구현Completebhan bhan08/11/202508/18/2025

Actions
4STEP #7424: Satellite Setting - OD 프론트 구현Completekim miseon08/11/202508/22/2025

Actions
4STEP #7425: Satellite Setting - OD Measurement Setting 프론트 구현Completekim miseon08/11/202508/22/2025

Actions
4STEP #7426: Satellite Setting - OP 프론트 구현Completekim miseon08/11/202508/22/2025

Actions
4STEP #7427: Satellite Setting - OM 프론트 구현Completehkgwon hkgwon08/11/202508/18/2025

Actions
4STEP #7428: Satellite Setting - AD 프론트 구현Completekim miseon08/11/202508/22/2025

Actions
4STEP #4233: 1.6 TestPlanned11/03/202512/31/2025

Actions
4STEP #4262: 1.6.1 Development server TestPlanned11/03/202512/31/2025

Actions
4STEP #4263: 1.6.2 Development server Test ClientPlanned11/03/202512/31/2025

Actions
4STEP #4264: 1.6.3 Production Server TestPlanned11/03/202512/31/2025

Actions
4STEP #4265: 1.6.4 ManualPlanned11/03/202512/31/2025

Actions
4STEP #4234: 1.7 DonePlanned12/01/202512/31/2025

Actions
4STEP #4266: 1.7.1 OpenPlanned12/01/202512/31/2025

Actions
4STEP #4267: 1.7.2 Final ReportPlanned12/01/202512/31/2025

Actions
Actions #1

dain Integrated Management System이(가) 9달 전에 변경

  • Subtask#4228이(가) 추가되었습니다.
Actions #2

dain Integrated Management System이(가) 9달 전에 변경

  • Subtask#4229이(가) 추가되었습니다.
Actions #3

dain Integrated Management System이(가) 9달 전에 변경

  • Subtask#4230이(가) 추가되었습니다.
Actions #4

dain Integrated Management System이(가) 9달 전에 변경

  • Subtask#4231이(가) 추가되었습니다.
Actions #5

dain Integrated Management System이(가) 9달 전에 변경

  • Subtask#4232이(가) 추가되었습니다.
Actions #6

dain Integrated Management System이(가) 9달 전에 변경

  • Subtask#4233이(가) 추가되었습니다.
Actions #7

dain Integrated Management System이(가) 9달 전에 변경

  • Subtask#4234이(가) 추가되었습니다.
Actions #8

park sooyeol이(가) 5달 전에 변경

  • 상태을(를) plan에서 development(으)로 변경되었습니다.
Actions #9

hwang jinouk이(가) 4달 전에 변경

  • 유형을(를) general에서 4STEP(으)로 변경되었습니다.
  • 상태을(를) development에서 Planned(으)로 변경되었습니다.
Actions #10

hwang jinouk이(가) 4달 전에 변경

  • 상태을(를) Planned에서 Proceeding(으)로 변경되었습니다.
Actions #11

CHOI DASOL이(가) 24일 전에 변경

  • 제목을(를) 1 Project Task에서 ProjectTask(으)로 변경되었습니다.
Actions

내보내기 Atom PDF